Reports until 16:04, Thursday 19 February 2015
H1 General
jeffrey.bartlett@LIGO.ORG - posted 16:04, Thursday 19 February 2015 (16820)
Ops Day Shift Summary
LVEA: Laser Hazard
Observation Bit: Commissioning  

07:15 Cris – Cleaning in the LVEA
08:00 - Cannot login to CR terminals – CDSFS0 had crashed. Ryan rebooted computer 
08:00 Jamie – Restarting Guardian to pick up new patches
08:15 Corey – 3IFO work in H2 Squeezer Bay 
08:18 Elli & Dave – Working around HAM6 
08:20 Filiberto – Working on PR3 OpLev
08:30 Betsy – Running TFs on SRM and SR2
08:40 Andres – In LVEA looking for tooling
08:45 Andres – Out of the LVEA
09:00 Kyle – Looking for the bolts for the HAM1 door – Prep for pump down
09:45* Kyle – Out of the LVEA
09:55 Jodi – Working at Mid-Y on 3IFO stuff
10:00* Dave & Elli – Out of the LVEA
10:00* Filiberto – Out of the LVEA
10:30* Corey out of the LVEA
12:13 Vending provider on site to stock machines
13:48 Apollo – On site to work on CDS AC units
15:35 Kyle – Going to End-X to recover tools for the HAM1 vacuum work