Estimates are at least 10 working days needed to complete the 3IFO tasks before the end of March. To reach this goal, Tuesday’s and Thursday’s will be open access to LVEA and VEAs and noisy work (craning, forklifts, etc.) will be permitted between 08:00 and 16:00. During this time, the LVEA and VEAs can be transitioned to Laser Safe as needed. Always check in with the operator before starting a task. The 08:00 to 10:00 noise windows are suspended while the extended Tuesday and Thursday noise hours are in effect. Summary: No commissioning and noisy work on Tuesday and Thursday between 08:00 and 16:00. Commissioning during all other hours. These times can be altered due to special requirements, with agreement of the commissioners. Fred brought up the need to review and refine the alarms, alarm handlers, and system monitoring. Fred asked that that the staff think about how these systems can be improved. This will be the subject of the next Science Team meeting. Tuesday 02/24 - GV5 and GV7 will be closed to support the pump down of HAM1. Kyle – will be installing the remaining bolts on the HAM1 doors. Filiberto – Will be shutting down the Test Stand in the West Bay area to prep for rack removal. Jim – running TFs on HAM4