LVEA: Laser Hazard Observation Bit: Commissioning 07:15 Cris & Karen – Cleaning in the LVEA 07:15 Jodi – In the LVEA 07:52 Corey – Working in the Squeezer Bay 08:05 Elli & Dave – Working on IOT2R 08:20 Jim – Running TFs on HAM4 10:00 Corey – Out of the Squeezer Bay 11:00 Kyle – Going to HAM5 area to get bolts for HAM1 11:14 Kyle – Out of the LVEA 11:17 Keita – Going into the LVEA to look for 3IFO parts 11:21 - Adjusted the ISS diffracted power from 5.2% to 8.1% 11:35 Keita – Out of the LVEA 12:13 Elli & Dave – Out of the LVEA 12:49 Ed – Retrieving totes from Mid-Y 13:21 John, Bubba, & Kyle – Going to Mid stations and end stations to check the weather stations 13:42 Dan & UM Students – Going to LVEA roof. 13:54 Ed – Opening high-bay roll-up door to bring in totes. 14:10 Ed – Going back to Mid-Y 14:30 Ed – Back from Mid-Y 15:05 John, Bubba, & Kyle – Back from mid and end stations