Reminder: Morning meetings are now on Monday, Tuesday, and Thursday at 8:30.
SEI:
-
Looking at pump station power supplies, noisy pressure signal
-
Stage 2 BS sensitive to rotations
-
ISI in can in staging building, moving to LVEA on Thursday
SUS
-
Betsy continuing work with SDF
CDS
-
Pull racks in H2 building on Tuesday
3IFO
-
Full speed ahead on all subsystems
-
Jeff wants to bring a forklift around in the morning
-
Betsy will turn off the cleanroom next to HAM 2/3 tomorrow
Vac
-
The power supply next to HAM1 will be leaving
-
Kyle will be working with BSC3
-
Richard will be relocating vacuum cables
FMCS
-
Over the weekend there was a temperature excursion at both end stations. The temperature dropped and will be monitored closely from now on.
OpLev
-
The grouting project was a much larger task than previously anticipated, so they will test it on a single one first sometime in the future.