Displaying report 1-1 of 1.
Reports until 17:24, Monday 16 March 2015
LHO VE
bubba.gateley@LIGO.ORG - posted 17:24, Monday 16 March 2015 (17284)
Beam Tube Washing
Scott L. Ed P. Chris S.

The crew relocated lights and equipment this morning. We will be starting at the single door between X-1-5 and X-1-6 double doors and working toward the Mid station. We started vacuuming beam tube supports this afternoon and took dirty samples on the tube. Results posted on this entry. These are some of the dirtiest areas we have seen so far.
A new generator was purchased Friday, however it still needs to be shipped here. A rental generator was picked up this morning to get us by until the new unit arrives. 
Non-image files attached to this report