LVEA: Laser Hazard Observation Bit: Commissioning 07:00 Karen & Cris – Cleaning in the LVEA 07:45 Bubba – Chiller delivery from LLO, Bubba unloading truck at Mid-X 08:15 HFD – On site with Richard at Mid-X 08:25 Adjust ISS diffracted power from 5.5% to 8.2% 08:43 Corey – Going into Squeezer bay for 3IFO work 08:50 Filiberto – IN LVEA making a survey of racks 09:00 Corey – Out of squeezer bay 10:00 Corey – Going into squeezer bay for 3IFO work 10:10 Bubba – Finished unloading truck at Mid-X – Big Red has been parked 10:30 Corey – Out of squeezer bay 11:15 Ken – Working on CER 12:47 HFD on site for fire alarm maintenance 14:20 Richard – Going to Mid-X 14:35 HFD finished testing the OSB fire alarms