Displaying report 1-1 of 1.
Reports until 09:36, Monday 23 March 2015
H1 General
edmond.merilh@LIGO.ORG - posted 09:36, Monday 23 March 2015 (17383)
Morning Meeting Summary

SEI - hoping to get a new isolation filter installed on BS stage2.

SUS- nothing to report

CDS - ESD filters will be installed

3IFO - Tuesdat activities will include tagging and bar-coding of TCS and ISC items. Calum will be on site next week. Bubba is continuing to connect piping o containers for N2 purging.

FACILITIES - BTE cleaning is ongoing. Semi-annual lubrication of axial fans for the ventilation sytems will start today with the mid stations and may move to the corner statinos by today. Filters will NOT be removed.

Displaying report 1-1 of 1.