SEI - hoping to get a new isolation filter installed on BS stage2.
SUS- nothing to report
CDS - ESD filters will be installed
3IFO - Tuesdat activities will include tagging and bar-coding of TCS and ISC items. Calum will be on site next week. Bubba is continuing to connect piping o containers for N2 purging.
FACILITIES - BTE cleaning is ongoing. Semi-annual lubrication of axial fans for the ventilation sytems will start today with the mid stations and may move to the corner statinos by today. Filters will NOT be removed.