Reports until 16:08, Friday 03 April 2015
LHO VE
bubba.gateley@LIGO.ORG - posted 16:08, Friday 03 April 2015 (17673)
Beam Tube Washing
Scott L. Ed P. Chris S.

Yesterday the crew cleaned 52 meters of tube and 67 meters today to X-1-8 double doors. Results are posted here.

The extraordinary accomplishment of cleaning over 90 meters on 3-31 was very much appreciated, however I have asked the crew to consider a more reliable pace and not burn themselves out. I reminded them that we are only 20% complete with the overall task.

Monday will be spent relocating equipment, lights, and support vehicles. 