ER-7 is scheduled for mid-June. There will be a short “annealing” run just before the ER-7 run. Seismic: Running TFs on BS and ITMX. BRS: Software crashes about every two weeks. Ops will check the BRS status daily. CDS: Finished connecting the Dew Point sensors for the 3IFO storage containers. VAC/FMC: HAM6 is still pumping. Hope to transition Ion pump today. Beam Tube cleaning of the X-Arm is 25% complete. There will be a safety meeting at 15:00 in the LSB auditorium. There will be painters on site working in the VPW, LSB, and OSB. PSL: Work continues on the FSS. Comm: Tuning and alignment work on the Mode Cleaner and the HWS.