TCS Y CO2 Table
The 50W laser is now running on the TCS Y table. Unfortunately the issues with the HWS kept us from being able to start trying to align everything. The projection beam is currently being dumped. Also took the opportunity to install the DC power switch. Currently the Y arm has the switch installed while the X arm does NOT have one installed. While setting up the IR fault kept triggering; if the laser suddenly shuts off that would be my first suspect.