bubba.gateley@LIGO.ORG - posted 15:36, Friday 24 April 2015 (18057)
Beam Tube Washing
Scott L. Ed P. Chris S.

Yesterday the crew cleaned 82 meters ending 12 meters north of HNW-4-012.

Today the crew cleaned 61 meters ending 13.7 meters north of HNW-4-015. The crew also serviced the generator today.