david.barker@LIGO.ORG - 10:26, Monday 27 April 2015 (18074)

Additional CDS work to Tuesday maintenance: upgrade end station ALS models to RCG branch2.9, use new RFM_DELAY feature for all ALS RFM senders to remove ASC receive errors.

Correction on injection work, no upgrade of the hardware injection machine, new h1calcs model to be installed.