H1 TCS (TCS)
greg.grabeel@LIGO.ORG - posted 18:23, Wednesday 29 April 2015 (18122)
HWS rough alignment
Nutsinee, Greg
Alignment continued in two parts today. We first aligned the SLED beams to the irises on the table while waiting for a green beam to return. Once we got a green beam we attempted to align the SLEDs to the green beam. The Y side looks like it could use some continued refinement, while the X side continued to give us fits until the commissioner asked to give him back the interferometer. 