Reports until 10:08, Monday 11 May 2015
H1 General
jeffrey.bartlett@LIGO.ORG - posted 10:08, Monday 11 May 2015 (18356)
08:30 Morning Meeting Minutes
Seismic: No activities
Suspensions: No activities
CDS: Finish making CPS cables – Will install at BSC1, 2, & 3 during the Tuesday window.
	     Continuing with work on AA/AI boards in H2 electronics building.
PSL: Tuesday work on RefCav alignment and Laser/Chiller tripping problem.
FMC: Painting in OSB 
Vacuum: Bake-out of RGA at End-X
Software: Work on timing distribution system