Ops Shift Summary
LVEA: Laser Safe
Observation Bit: Commissioning 
  
07:00 Karen & Cris – Cleaning in the LVEA
08:17 Hugh – Going into the LVEA
08:28 Party Rentals on site to setup
08:30 Jodi & Bubba – 3IFO work in LVEA
08:30 S & K Electronics – Electrical work at End-Y and End-X
08:33 Cris – Going to End-X and Mid-X
09:00 Richard – Going to End-Y
09:05 Audio/Visual person on site to setup
09:10 IO Power Supplies & 18-bit DACs (Richard)
09:15 Reprogramming of IO Chassis Timing at EY (Dave & Jim)
09:20 Beckhoff Code Change (Patrick)
09:28 Praxair on site for Nitrogen delivery
09:52 Jim & Dave – At Mid-Y for PEM chassis swap
10:15 Jim – Shutting down Seismic computers for Work Permits 5207, 5205, 5204
12:10 Jim & Dave – Going to End-Y
12:30 Jim & Dave – Back from End-Y
12:56 Jim & Filiberto – Shutting down SUS computers for Work Permits 5207, 5205, 5204 
13:49 Jeff K – End-X doing SUS measurements
14:00 – 15:30 – Tours in LVEA and Control Room
15:02 Jim & Dace – Shut down PSL & ISC frontends for Work Permits 5207, 5205, 5204
15:03 Catering group on site to clean up after lunch