Reports until 09:34, Tuesday 26 May 2015
H1 General
vernon.sandberg@LIGO.ORG - posted 09:34, Tuesday 26 May 2015 (18616)
Proposed Calendar for the ER7 Run

Engineering Run 7

Schedule

1 Start of Calibration for ER7 (starts after maintenance at LHO)   Tuesday, 2015 May 26 12:01 pm PDT, 2:01 pm CDT
2 End of Calibration for ER7   Friday, 2015 May 29 12:01 pm PDT
3 Start of "Annealing" for ER7   Friday, 2015 May 29 12:01 pm PDT
4 End of "Annealing" for ER7   Tuesday, 2015 June 2 7:59 am PDT
5 Maintenance (four hours every Tuesday 8:00 - Noon local time)   Tuesday, 2015 June 2 8:00 am - Noon
6 Buffer before start of ER7, to be used as needed   Tuesday, 2015 June 2 12:01 pm PDT - Wednesday, 2015 June 3 7:59 am PDT
7 Start of ER7   Wednesday, 2015 June 3 8:00 am PDT, 10:00 am CDT
8 Maintenance   Tuesday, 2015 June 9 8:00 am - Noon
9 End of ER7   Monday, 2015 June 15 7:59 am PDT, 9:59 am CDT
10 Start of Vent at LHO   Monday, 2015 June 15 8:00 am PDT, 10:00 am CDT

Daily Global ER7 Run Status and Planning meeting will take place daily at 1:00pm PDT / 2:00pm CDT / 3:00pm EDT on the JRPC "TeamSpeak" channel. The plan is for a short meeting that provides updates and plans for the two interferometers and the data analysis community. This meeting will start on Tuesday, May 26, 2015.