bubba.gateley@LIGO.ORG - posted 15:47, Friday 05 June 2015 (18913)
Beam Tube Enclosure Joint Repair
Chris S.

Beginning 120 meters from the corner station on the X-Arm, 40 joints were cleaned and metal strips attached. 
Caulking still needs to be completed on those joints. 