ER7 will end at 08:00 on Sunday the 14th. The Vent prep work will start Sunday the 14th. Betsy will be the vent coordinator for the End-X and End-Y activities Hugh will be the vent coordinator for the HAM-6 activities For the vent plan, see aLOG 19085 Beam tube cleaning continues on the X-Arm Bubba - working on fan repairs in the Mechanical building Kyle – Prep work for the vent. Goal is to have the doors ready to come off at 12:00 Monday the 15th Peter – Will transition the end stations to Laser Safe by locking the laser enclosures and verifying all view ports are in place. The laser will not be shut down until Monday when the doors are ready to come off.