LHO VE
kyle.ryan@LIGO.ORG - posted 17:26, Wednesday 17 June 2015 - last comment - 18:46, Thursday 18 June 2015(19207)
misc. vacuum activities
Kyle -> Soft-closed GV7 and GV5 -> Vented HAM6 

Bubba, Hugh, Jim W. -> Removed HAM6 South and East doors 

Kyle, Gerardo -> Installed NEG and TMDS reducer nipple+valve+elbow at X-end 

Danny S., Gary T., Gerardo, Kyle -> Hung North door on BSC10 

(NOTE: Noticed ~1 hour before hanging door on BSC10 that the purge-air drying tower had been left off since tying-in the 1" TMDS line on Monday afternoon -> Turned it back on and notified the ETMY discharge crew
Comments related to this report
kyle.ryan@LIGO.ORG - 18:46, Thursday 18 June 2015 (19236)
Forgot to log -> Purge-air measured <-39 C just prior to venting HAM6