Scott L. Ed P. 6/18/15 Cleaned 39.8 meters of tube ending at HNW-4-082. Test results posted on this A-Log. Remove and begin re-hanging lights in next section north. 6/19/15 Completed hanging lights, start vacuum of support tubes and spraying of heavily soiled floor areas with water/bleach solution. Cleaned 20.8 meters of tube.