Reports until 15:58, Monday 22 June 2015
H1 General
edmond.merilh@LIGO.ORG - posted 15:58, Monday 22 June 2015 (19265)
Daily Ops Summary

08:00 GRB alarm sounding. Will investigate for the exercise.

08:05 Alarm Handlers restarted.

09:00 Heintze to HAM6 area to get ready for Black Glass install

09:07 Bartlett o end stations to disable "monitor2" dust monitors

09:14 Heintze back from LVEA

09:25 Fil and Richard to MY and EY to measure for new vacuum cables

09:44 Calum ad Matt out to HAM6

09:46 Bartlett back

09:57 Corey out to LVEA to begin replacing handles

10:15 Bubba to crans a table and a small cleanroom over to the HAM6 area. There is no worl permit for this but John Worden gave his approval.

10:17 FIl and ichard back from Y arm

10:45 Karen and Christina to EY

11:17 Karen and hristina leaving EY and goin to MY

11:25 Karen and Christina skipped MY and are in the LVEA to clean a clean room by HAM6

11:30 Corey done in LVEA

12:15 HAM 6 crew out

13:12 Corey out to End stations to change out handles on ISC I/O tables

13:12 HAM6 crew back out into LVEA.

13:42 Jordan out to EY. PEM

14:23 Corey back from end stations

14:55 McCarthy out to the LVEA with interviewee and Ryan

15:07 Jordan back from EY

15:34 Hugh to EX to unlock HEPI