Reports until 15:54, Tuesday 23 June 2015
H1 General
Link
cheryl.vorvick@LIGO.ORG -
posted 15:54, Tuesday 23 June 2015
(19298)
Ops Day Summary:
Ops Day Summary:
10:00AM Tour
11:15Am Tour
9:32AM Jordan, PEM, EX
9:50AM Jason/Ed, ITMX/Y Oplev
10:20AM Christine/Karen, EX and MX and MY cleaning
10:30AM Jeff, tools to HAM6 crew
10:43AM Paradise Water delivered
10:54AM Keita to HAM6
11:36AM Dave, EY timing cables, temporary setup
11: 40AM Sudarchan/Jordan, EY, WP
5301
11:45AM Patrick, added a temperature channel to Beckoff
12:02PM Christina & Karen done at Mid-X, going to Mid-Y
As of 2:00PM
Filiberto and crew taking a break for lunch, mostly done
HAM6 crew breaking for lunch, no official update, but helicoil tools were required earlier today
CP2 was filled today and the tank is currently at 65.6%
as of 2:06PM
2:06PM HAM6 crew back in the LVEA
2:41PM RO Water alarmed - emailed Bubba and John
3:15PM Sudarchan/Jordan, EY, WP
5301
3:30PM Dave - restoring nominal config. at EY
as of 4:00OM
work continues at HAM6
work continues at EY