The main installation activity today is closing out HAM6 work. In parallel a couple of tasks went on: (1) Balancing the ISI & (2) Retrofitting top glass plate so it can be installed.
HAM6 work is done in the chamber. The day ended with prep work (moving cleanrooms) so the doors can be installed on HAM6 on Monday. Before HAM6 is closed, the Signature Approval for Chamber Closure will need to be filled out (E1500273).
LVEA was transitioned to Laser SAFE this morning.
Day's Activities:
-
8:30: ETMx & ETMy charge measurements (Leonid)
-
9:00 Install a PCal Chassis at EX (Sudarshan)
-
9:15: HAM6ISI balancing beginning (Hugh & Greg)
-
9:30: OMC glass retrofit (Matt)
-
9:30: Grabbing AUX Cart from EY and bringing back to LVEA (Gerardo)
-
10:03: Cable swap for Low Noise ESD at EY to clear negatively-railed signals (Richard, TJ)
-
10:05-11:15: Troubleshooting PEM channels in LVEA (Jordan)
-
12:55: Pepsi truck
-
1:43: HAM6 in-vac work complete (OMC work done, ISI balanced, and SUS's given clean bill of health)
-
2:10: Final checks/inspection inside HAM6 (Hugh)
-
2:15: Ring Heater check (Nutsinee)
-
3:00: Bubba giving Rebolt a tour of piers/pylons/places to grout.