jonathan.berliner@LIGO.ORG - posted 16:11, Monday 19 December 2011 (1934)
Monday Ops Log

- IAS working in BSC8, installing corner cube
- Richard and SEI pulling cables
- SLC hoping for Wednesday installation
- Kyle looking for missing ConFlat flanges
- H1 PSL contractor coming Tuesday to lay down linoleum
- HAM1,2,3 - removing optics from HAM3
- Hanford Fire Department on site for testing