Reports until 16:06, Tuesday 30 June 2015
H1 General
jeffrey.bartlett@LIGO.ORG - posted 16:06, Tuesday 30 June 2015 (19391)
Ops Day Shift Summary
LVEA: Laser Hazard
Observation Bit: Commissioning 

07:30 Karen – Restocking garb at end stations 
07:30 Jodi – In LVEA for 3IFO and property management work
07:55 Sprauge on site to check traps – Joe D will escort
08:00 S&K Electronics – Installing conduit in X-Arm near end station
08:20 Jodi – Out of the LVEA
08:22 Patrick – Setting up test equipment for Beckhoff vacuum testing
08:25 Gerardo – Vacuum survey in LVEA
08:32 Bubba – Going to Mid-X looking at the grout
08:35 Richard – Going into LVEA for Beckhoff vacuum testing
08:39 Karen – Back from the end stations
08:40 Christina & Karen – Going into the LVEA
08:41 Gerardo – Out of the LVEA
09:02 Katie – In the LVEA checking Magnetometers
09:05 Kyle – Going to End-X
09:22 Jim – Working on HAM3 
09:26 Bubba – Back from Mid-X
09:27 Bubba – Going into fan room in the mechanical building
09:45 Jeff K. – Going into the CER
10:15 Richard & Patrick – Out of LVEA finished with test 
10:23 Jordan – In LVEA installing PEM antennas
10:56 Dave & Jim – Installing 18 bit DAC cards at HAM5 & HAM6
11:00 Rick & Jason – Going into PSL enclosure to look for replacement optics
11:13 Filiberto – In CER to swap EtherCAT chassis
11:15 Richard – Power cycling MC2 (and other suspensions) chassis
11:26 Richard – Out of the LVEA 
11:28 Kyle & Gerardo – Going to HAM6 to setup and start pumping
11:30 Jim – Going into LVEA to swap bad 18 bit DAC card
11:32 Rick & Jason – Out of PSL Enclosure
11:49 Filiberto – Out of the LVEA
12:04 Kyle & Gerardo – Going to End-X to recover leak checker
12:43 Kyle & Gerardo – Back from end station – Going to HAM6
12:48 Kiwamu – Restart LSC frontend model
13:18 Kyle & Gerardo – Out of LVEA – HAM6 is being pumped down
13:45 Sheila – Transition LVEA to laser hazard
14:06 Kyle – Going to HAM6 
14:08 Jordan – Out of the LVEA
14:36 Greg & Nutsinee – Going into the LVEA to start TCS chillers and check tables
14:46 Patrick – Pause replication & backup on H1conlog1-replica
15:45 Greg & Nutsinee – Out of the LVEA
15:55 Dave – DAQ restart
15:59 Kyle & Gerardo – Going to HAM6