H1 General
edmond.merilh@LIGO.ORG - posted 09:17, Monday 06 July 2015 (19448)
Morning Meeting Summary

VAC : pumping going fine. Y-arm to be opened tomorrow. X-Arm on Wednesday. Sloww process to valve-in new getter type pumps.

SUS: FE model changes to be done tomorrow. Betsy picking pu TMS investigations from two weeks ago.

SEI: Evals of FF. HAM6 HEPI Still locked. FE models update for Tues / sensor correction.

CDS: P-Cal cabling at both end stations. Richard/Fil will have a look at the TMS PDs. GPS cabling scheduled for rooftop on Tues.

COMM: Continued working on MICH FREEZE (silmultaneous DRMI locking)

FAC: X-Arm cleaning complete, Y-Arm cleaning ton commense tomorrow. Extra person, Rodney, added to cre to expedite.