H1 SYS
daniel.sigg@LIGO.ORG - posted 12:04, Monday 06 July 2015 (19451)
Commissioning planning for maintenance periods
 
A tentative plan of commissioning upgrades for the next 3 maintenence periods. The hope is to finalize all major commissioning upgrades by 7/28.
 
Maintenance period 7/7:
- Reboot servers/work stations 8am - 10am
- Complete SEI model changes for adding test points (BSCs)
- Switch main modulation to new RF source
 
Maintenance period 7/14:
- Install fast end station SUS computers
- Add additional ADC board for PI damping
- Updated SUS model to include new common part w/  DARM ctrl for roll/bounce damping
 
Maintenance period 7/21:
- Change master GPS clock to external Trimble unit (requires antenna)
- Change EX timing FO (to fix VCO reporting error)
- Install initial model for PI processing
 
TBD:
- Updated remote ESD monitoring/restart hardware
- Install second low noise ESD
- Install new ISS monitoring hardware
- Install EOM drivers
- Change PSL top periscope mount
 