Reports until 16:33, Monday 06 July 2015
LHO FMCS
bubba.gateley@LIGO.ORG - posted 16:33, Monday 06 July 2015 (19456)
SUPPLY FANS IN OUT BUILDINGS
The variable pitch actuators on all of the supply fans in each of the out buildings were exercised this afternoon. 

S.F. 01 at Mid X and S.F. 02 at Mid Y were found to be faulty. We are only operating 1 fan at each mid station so these can be repaired with no impact to the cooling of the buildings. 

I will look into ordering parts tomorrow.