All Times in UTC:
14:45 Jeff B out to LVEA to move cleanrooms
15:15 Andres out to LVEA to join Jeff
15:26 Karn and Christina to EY
15:36 Joe into LVEA to check on orklift batteries, Fire Extinguishers, eye-wash stations...etc
15:45 Hugh into the Bier Garden
15:47 Kyle to EY
15:52 Bubba goin to MX and EX
15:56 Karen and Christina leaving EY
16:07 Hugh out of LVEA and heading to EXto replace T240 with STS2. Back at 17:59.
16:16 Fil out to Ends to do P-Cal power (both) and magnetometer power for Jordan at EY
16:26 Betsy and Travis out to the LVEA to check for post-vent fodder.
16:39 Andres out
16:46 Jeff B out
17:02 Leaving EX cristina & karen
17:25 Restarting all SEI Models (Kissel)
17:30 Praxair called in to say a truck will be on-site in 15min (for "379" which is MX's CP6) & he mentioned that another truck will be heading to "380" (which is EX's CP8).
17:40 Noticed Beckhoff at EX went down, need to figure out how to remote login and restart.
17:53 pemmx rcg upgrade & pulling a card as well (Dave)
18:05 Continuing Vent clean up in the Cleaning Room (Betsy)
18:06 Heading into LVEA for hose (Joe)
18:10 TCS Chassis Install at EX & then to EY (Sudarshan, Vinny, & Jordan)
18:20 Gerardo said to keep an eye on EY pressure---any alarm for pressure increase
18:22 Gerardo on top of HAM6 (for how long?)
18:27 Kyle opening GV5 & GV7
18:38 Sudarshan turning on P-Cal LASER at EX
18:48 Fill reported back from Ends
18:49 Joe into LVEA
18:50 DAQ restart
19:13 Sheila heading to EX to restart slow controls computer
19:28 Kyle out of LVEA. GV 5,7 are now opened.
19:35 Sheila back from EX
19:48 Fill called from EX. Continuing work for PEM
19:51 Sudarshan back from EX
20:03 Dave re-boot somthing at EY
20:30 Kyle, John & Gerardo to EY to valve in NEG and valve out Turbo
21:15 John called from EY. Arm is open and Gauges are reading inconsistently. (2orders of magnitude)
21:19 Jordan and Vinny to EY WP 5336
21:20 Katie to EY, Mangetomoeter calibration.
21:21 Fil called from EY. While doing cabling, accidentally disconnected 12V oscillator source.
22:11 Nutsinee out to HAM4 to adjust alignment on HWS table
22:44 Dave and Jim at MX. Took PEM down to remove 18bit DAC.
22:47 Ellie out o HWS table to assist Nutsi
22:48 Jeff K, TJ and Leo to EX to debug ESD issue.