Displaying report 1-1 of 1.
Reports until 16:48, Friday 10 July 2015
LHO VE
bubba.gateley@LIGO.ORG - posted 16:48, Friday 10 July 2015 (19558)
Beam Tube Washing
Scott L. Ed P. Rodney H.

7/8/15
Cleaned 68 meters of tube, bellows, and crevices ending at HSW-2-093. Test results posted below.
Removed lights and started relocating equipment to next section and hanging lights.

7/9/15
Cleaned 79.6 meters of tube and ending at HSW-2-089. Bellows and crevices still need to be cleaned.

7/10/15
The bellows and crevices on the previous section were cleaned and tested. Results posted below.
The lights were removed and relocated to the next section. The crew started vacuuming the support tubes and capping them.   21 meters of tube cleaned.

 A total of 227.6 meters of Y-Arm tube has been cleaned.

 
Non-image files attached to this report
Displaying report 1-1 of 1.