patrick.thomas@LIGO.ORG - posted 16:01, Wednesday 15 July 2015 (19670)
Ops Summary
08:09 Ken working on GPS antenna on roof
08:46 Peter, Jeff B. to chiller room to look at chiller displays
08:52 Richard to roof
09:02 Peter, Jeff B. back
09:39 Travis to LVEA to look for part
09:45 Rebooted projector0 due to memory leak, Jim B. recreated credentials for seismic DMT
09:49 Travis back
11:26 Richard to DC power mezzanine to look at roof sections
11:32 Jeff B. to cleaning area
11:44 Richard back
12:17 Ken to electronics room to get measurements for drilling hole in building for GPS antenna cabling, then drill hole
12:58 Nutsinee to LVEA to take pictures of CO2 laser chassis
13:04 Nutsinee back
13:30 Ken done

Commissioners working on recovering IFO alignment.