H1 PEM
filiberto.clara@LIGO.ORG - posted 16:40, Thursday 23 July 2015 - last comment - 17:04, Thursday 23 July 2015(19881)
Cosmic Ray Detector - Installation
Items completed today:
1. High Voltage Power Supply was installed (PEM-C1) and HV outputs were verified
2. Cosmic Ray Electronics D1500202 was installed (PEM-C1)
3. All BNC and MHV cables were terminated
4. Raymond Frey looked at outputs of cosmic detector - all within spec

Signals still need to be entered into DAQ (ongoing).
Comments related to this report
david.barker@LIGO.ORG - 17:04, Thursday 23 July 2015 (19884)CDS, DAQ

WP 5382 has been opened to add the Cosmic Ray channels to the h1pemcs model. Currently one channel will be added to the DAQ at 16kHz.