H1 SYS
daniel.sigg@LIGO.ORG - posted 09:55, Friday 24 July 2015 (19900)
Commissioning planning for maintenance periods

This is an update to alog 19451.

All tasks which have been scheduled for the maintenance periods of 7/7, 7/14 and 7/21 have been completed. Furthermore, all pending SUS/SEI ECR model changes have been implemented. However, the update to the new faster end station SUS computers has been proven somewhat unstable.

Completed tasks:

Maintenance period 7/28:
  • Finish installation of low noise ESD in EX
  • Either install fix for ADC/timing errors in end station SUS computers, or
  • Revert EY back to old computer/software
  • Convert all front-end code to RCG 2.9.6 (O1 release)
  • Boot new ASC IMC model

Maintenance period 8/4:

  • Finish fix for ADC/timing errors in end station SUS computers
  • Install EOM driver (optional)

Maintenance period 8/11:

  • Smooth sailing...