This is an update to alog 19451.
All tasks which have been scheduled for the maintenance periods of 7/7, 7/14 and 7/21 have been completed. Furthermore, all pending SUS/SEI ECR model changes have been implemented. However, the update to the new faster end station SUS computers has been proven somewhat unstable.
Completed tasks:
-
Reboot servers/work stations
-
Complete SEI model changes for adding test points (BSCs)
-
Switch main modulation to new RF source
-
Install fast end station SUS computers
-
Add additional ADC board for PI damping
-
Updated SUS model to include new common part w/ DARM ctrl for roll/bounce damping
-
Change master GPS clock to external Trimble unit (requires antenna)
-
Change EX timing FO (to fix VCO reporting error)
-
Install initial model for PI processing
-
Updated remote ESD monitoring/restart hardware
-
Remaining ECRs for SUS/SEI model changes
-
Added damping to the PSL periscope
-
Increased ISS bandwidth
Maintenance period 7/28:
-
Finish installation of low noise ESD in EX
-
Either install fix for ADC/timing errors in end station SUS computers, or
-
Revert EY back to old computer/software
-
Convert all front-end code to RCG 2.9.6 (O1 release)
-
Boot new ASC IMC model
Maintenance period 8/4:
-
Finish fix for ADC/timing errors in end station SUS computers
-
Install EOM driver (optional)
Maintenance period 8/11: