bubba.gateley@LIGO.ORG - posted 15:45, Friday 24 July 2015 (19910)
Beam Tube Washing
Ed P. Rodney H. Mark L.

7/22/15
The crew relocated the lights and generator after testing the previously cleaned sections, results posted in this entry. 

65 meters of tube cleaned ending 3.8 meters east of HSW-2-062.

7/23/15
76.2 meters of tube cleaned today ending at HSW-2-058. The cleaned sections were tested and the generator relocated. Test results also posted here.

7/24/15
The vacuum nozzle that we originally modified for a lower noise level has lost the Viton strips that were installed. I reinstalled thicker rubber strips and reinforced these with an aluminum backing strip. This was only tried for a few hours this afternoon so time will tell.

 We were able to clean 79 meters today ending at HSW-2-054. We began relocating the generator and lights.

Total meters of Y-Arm tube cleaned = 907.  