Scott L. Ed P. Rodney H. 7/27/15 The crew finished moving equipment and hanging lights. 59 meters of tube cleaned ending at HSW-2-052. Tested clean sections and started moving cords and generators. 7/28/15 81.5 meters of tube cleaned ending at HSW-2-047. 7/29/15 79.6 meters of tube cleaned ending at HSW-2-044.