LHO VE
bubba.gateley@LIGO.ORG - posted 15:57, Wednesday 12 August 2015 (20487)
Beam Tube Washing
Scott L. Ed P. Rodney H.

8/11/15
After filling the water tank, the crew moved the fans and re-strung the lights. 45 meters of tube and bellows were cleaned ending at station HSW-2-012. Cleaning results posted here.

8/12/15
60.6 meters of tube and bellows cleaned ending at station HSW-2-009. 