ISC: Did some good work last night, changed ASC input matrix to a, hopefully, good setting.
CDS: PEM antennas, noise on tigger signals, Vault seismometer.
PSL: PMC work on Tuesday. OpLevs currently behaving.
VAC: Today they will be driving between Y28 and X28 and dropping off things.
Fac: Beam tube cleaning ongoing, front double doors do actually lock (see Bubba if you need instructions on how to lock properly)
Monday is the start of ER8, there will be 3 weeks till the O1.
Week 1 - Annealing. The intent is to bring the IFO to a stable operating state.
Week 2 - Calibration. Stability, stability, stability.
Week 3 - PEM injections and commissioning cleanup.
Then if all is well at both sites, O1.
(Please see JRPC site for a more detailed and accurate schedule)