hugh.radkins@LIGO.ORG - posted 12:54, Wednesday 18 January 2012 (2064)
BSC8 HEPI State for Initial Alignment
As IAS told us last night we were 0.4mm South, we disconnected the Vertical Actuators and then based on the Dial Indicators moved a total of ~1/2mm North.  After this, IAS told us we were 0.9mm too far North...What gives?

Jason checked his numbers and confirmed.  We moved the HEPI back South ~1mm and now IAS says we are 0.03mm South.

So now the ACB is being aligned--when they are done, SEI will change/add Viton to vibration absorbers.