Installation began yesterday on the fire suppression system for the new DCS room by a 2 man crew from Fire Protection Specialist. They started working on conduit runs for the warning lights, pull handles and abort switches. This portion of the install is expected to be completed by EOB tomorrow. Long lead items such as the tank and agent are expected to arrive next week and will be installed along with the piping and spray nozzle.