(All time in UTC)
15:15 Christina opening the roll-up door, OSB receiving area
15:30 Christina done
16:36 Kiwamu to electronics area by PSL and HAM6
16:59 Sudarshan has been doing Pcal swept sine. Now done.
Kiwamu done
17:00 Observing intent bit set. SDF hasn't been cleared at this point. See attachment.
17:34 Bubba to Mid station
18:03 Intent bit switched to Commissioning. Flipped DHARD 20-30 Hz BP filters.
18:05 Intent but switched back on
18:33 Kyle to beam tube near EY to make measurement. 300 m away from EY.
18:36 Wind picking up. Reaching 30 mph.
Intent bit swited to Commissioning. Daneil to CER.
18:53 Daniel back. Intent bit Observing.
19:00 Calibration group taking over. Bring interferometer to down. Intent bit set to Commissioning
19:11 Kiwamu to LVEA doing OMCDCPD measurement
19:23 Fire protection Specialists back on site. Fire suppression in Network Room.
19:30 Sheila to LVEA looking for Kiwamu.
19:38 Kyle back
20:47 Sheila locking MICH
Something water on site. Couldn't hear the guy. Let a white pick-up truck in.
21:09 Bubba done
21:42 Travis, Sudarshan, Darkhan to EY (Pcal calibration)
19:02 Hand the ifo over to Patrick