Reports until 09:39, Tuesday 01 September 2015
H1 GRD
jameson.rollins@LIGO.ORG - posted 09:39, Tuesday 01 September 2015 - last comment - 15:13, Tuesday 01 September 2015(21088)
Three new guardian DIAG nodes added: CRIT, SDF, EXC

I have added the following three guardian DIAG nodes:

DAQ restart required to acquire new channel names.

These nodes will all be folded under the IFO top node, but have not yet.  Waiting for go ahead from ops...

I'm also in the process of updating the GUARD_OVERVIEW screen to add these new nodes.  I will post when that screen has been updated.

Comments related to this report
betsy.weaver@LIGO.ORG - 15:13, Tuesday 01 September 2015 (21103)

In discussion, we are proceeding with tying this into the READY bit.  Expect an alog from Jamie - but be aware that you may need to look further at some things if you cannot hit the INTENT bit.  For example, all SDF must be clean (not red) now.  You may need to consult the on-call commissioner if you cannot interpret and address any red SDF differences before going into observation mode.  We have some time before the start of O1, so we'll be troubleshooting this if needed this and next week.