Yesterday the grout forms were placed and secured around the HEPI piers at HAM 1 with the intention of pouring the grout on the next maintenance day 09/15. I also checked the nitrogen flow at all of the LTS containers. I was also able to crane the TCS chiller that I craned over the tube last week for Jodi back over the tube for Jeff B.