Reports until 09:30, Monday 21 September 2015
H1 General
travis.sadecki@LIGO.ORG - posted 09:30, Monday 21 September 2015 (21737)
Morning meeting notes

LDAS switch has failed over the weekend, due to be replaced.  This caused several sites to be unavailable (Omega glitch plots and summary pages to name a few).

VE will need access to X-2-8 this week.  Will notify operators.

HFD on site tomorrow for annual fire inspection.

Air compressor isolators in hand.  Installation on hold until further notice.

Tuesday maintenance activities scheduled for tomorrow: