Displaying report 1-1 of 1.
Reports until 00:02, Tuesday 22 September 2015
H1 General
jim.warner@LIGO.ORG - posted 00:02, Tuesday 22 September 2015 (21769)
Shift Summary
15:30 Ken working at warehouse, hooking up wiring for fire suppression
system
16:00 ChrisS and JoeD working on arm, recalled at 18:20, 
16:00 Kiwamu and JeffK working on calibration and hardware injections for a couple minutes
16:15 Bubba and JohnW driving down Xarm to investigate an air compressor 250m from EX, done 17:20
16:45 Hugh at EY
16:45 Fil to CER, out at 16:55
17:00 Hugh at EX, out at 17:10
17:55 Hugh in Mechanical Room checking HEPI fluid levels
~22:40 Range starts getting ratty and DMT OMEGA scans on control room display shows we are getting glitchy, numerous ETMY saturations
Displaying report 1-1 of 1.