Reports until 12:17, Tuesday 22 September 2015
H1 General
nutsinee.kijbunchoo@LIGO.ORG - posted 12:17, Tuesday 22 September 2015 (21794)
Mid Day Shift Summary

15:00 Pepsi trucks on site

           Christina checking out bidgs

15:02 Jeff: Dust Monitor work

15:35 Fil, Andreas, and Leslie to CER, LVEA to take pictures of the racks.

15:41 Hugh left X end

           Patrick to MidY to look for spare Bekhoff

           Bubba out of LVEA

15:43   Jodi out of LVEA

15:46 Jeff added 150 mL to PSL chiller

15:49 Jason to Mid X to check on 3IFO Oplev spare

15:51 Praxxair on site - one to EX driving real slow.

           Bubba using forklift to move the barricades

16:03 Patrick back

           Richard just finished w/ the vault. Heading to Mid X.

           Fire department here to test fire hydrant.

           Spotted Praxxair at Mid Y. Apparenlt there are two Praxxair trucks.

16:09 Christina + Karen to EX and EY. Just to look. No cleaning.

16:13 Peter to change room to take pictures of the eyewares.

           Sheila and Keita checking on Fil at CER.

16:20 Jason out

16:24 Peter done in the change room.

16:27 Richard back

16:39 Mitchell + Hugh checking on 3IFO stuff at North bay

16:42 Karen + Christina leaving EY

         Fire department to EY

16:47 Mike + SPIE camera crew out of LVEA

16:50 Richard to EY and MY to pick up Beckhoff stuff

16:51 Bubba to fan room to work on Sf3

16:57 Mike + SPIE crew driving down X arm

17:11 Joe done checking extinguisher (EX, EY, LVEA)

17:14 Richard back

17:18 Mike back

17:19 Daniel pulls some quipment out of electronics room

17:25 Fil to EX

17:32 Daniel out

17:52 Hydrant shut off at corner station

17:53 Jeff B. to mezzanine area

17:54 Jim restart H1 nds0 and nds1

17:44:35-17:55:47 Lots of ETMY saturations

18:05 Kyle starting pumps at MY (leak detection)

18:11 Fil and Andreas at EY

18:12 Cheryl and Ed doing LVEA sweep

18:20 Dave restart broadcaster

18:24 Hugh to both end stations to photograph stuff

18:30 Jeff B. out. And ging to bring up roll up door 3 feet to move in boxes (not heavy).

18:35 Evan and Jenne to LVEA (ISC rack)

18:37 Hugh at EX. Ken drilling hole on the beam tube concrete

18:05:36-18:34:34 Hell of ETMY saturations

18:41 Jeff B. done. He also added water to TCS chiller =D

18:45 Evan and Jenne out

18:46 Fil to EY to pickup stuff.

19:01 Hugh at EX. Fil just left EX.

19:07 Fire guy done checking extinguisher.