Displaying report 1-1 of 1.
Reports until 00:11, Saturday 26 September 2015
H1 General
edmond.merilh@LIGO.ORG - posted 00:11, Saturday 26 September 2015 (21968)
Shift Summary - OWL Transition

TITLE: Sep 26 OWL Shift 07:00-15:00UTC (00:00-08:00 PDT), all times posted in UTC

STATE Of H1: Observing

OUTGOING OPERATOR: Patrick

QUICK SUMMARY:. IFO Locked at 68Mpc/22.9W. No injections are running. All lights are off in LVEA, MID, END and PSL. Wind is <10mph. Microseism seems to be riding steady at ~.1um/s for the last few hours following an earthquake. EQ seismic took a little hop from ~ .2 um/s to .1um/s due to a small earthquake in the Portugal area. It appears that at 07:09UTC there was some raised level of noise activity in DARM from 25Hz and below. This only lasted about 1 minute.

Displaying report 1-1 of 1.