Reports until 09:22, Monday 05 October 2015
LHO General
corey.gray@LIGO.ORG - posted 09:22, Monday 05 October 2015 (22234)
Monday Morning 8:30 Meeting

Summarized H1 issues from last Fri/Sat & how we did over the weekend:  Combination of environment & ALS glitching possible culprit for issues Fri/Sat.  However we've been locked since about noon on Sat (going on 45hrs).

RF45 appears stable (will prob hold off on swapping cable until/if issue comes back & NOT address during Maintenance.  Only address if needed).

Also discussion of "Freeze".  Sounds like we are still in a partial freeze.  

There was discussion about allowing Beam Tube repairs (will be discussed offline).

Commissioning & Any Invasive Activities:  

Regular Tues Maintance Activities 

There are activities which occur every week and these do not require a Work Permit, but need to be done on a recurring basis.  A short list of these (also on whiteboard) is:

10/6 Tues Maintenance Activities

Ed is Operator on shift (& TJ is available as a secondary operator, if needed)