Reports until 14:08, Tuesday 06 October 2015
LHO General
thomas.shaffer@LIGO.ORG - posted 14:08, Tuesday 06 October 2015 (22275)
LVEA Swept

Betsy, TJ

Walked through and followed the checklist as closely as we could. There is still a power distribution box on near ISCT6 that seems to be plugged into many differenet things. Last week this was deemed OK for the time being so we left it as is. There are many cables still hanging from racks not plugged into anything. These will need to be cleaned up in a future Maintenance Day.

Lights are OFF

Monitors/Work Stations OFF

Wifi OFF

Phones disconnected and batteries taken out of handsets

Cranes in "parking spots"

Cleanrooms OFF

ISC table fans OFF

Forklifts are not charging