Displaying report 1-1 of 1.
Reports until 00:24, Monday 12 October 2015
H1 AOS
jeffrey.bartlett@LIGO.ORG - posted 00:24, Monday 12 October 2015 (22427)
Ops Evening Shift Summary
Activity Log: All Times in UTC (PT)

23:00 (16:00) Take over from TJ
02:30 (19:30) Jeff K. left the site
03:57 (20:57) Chris – Running hardware injections for the next 72 minutes. 
			Approved by Mike L., Notified LLO, Will not drop out of Observing
04:30 (21:30) GRB Alert – In one hour stand down
04:58 (21:58) ETMY saturation event during GRB stand down
05:30 (22:30) Finished one hour stand down. 
06:15 (23:15) Chris – Restarted hardware injections
07:20 (00:20) Turn over to Cheryl
	

Title: 10/11/2015, Evening Shift 23:00 – 07:00 (16:00 – 00:00) All times in UTC (PT)

Support: Jeff K, 

Incoming Operator: Cheryl

Shift Summary: 
- 03:57 – Chris running hardware injections. He has Mike’s approval and did not go out of Observing
- 04:30 Received GRB alert. Both sites in Observing mode. In stand down for 1 hour
Chris has stopped the hardware injections he was running.  Per Verbal Alarm - Last injection stopped at 04:28:17, the GRB was time stamped at 04:30:28.  
 	
Good shift. IFO locked in Observing for 14 hours. Low wind and seismic. There were several ETMY saturations. There were 3 mag 5 or greater earthquakes during the shift, but these did not noticeably affect the IFO.      